|
| |
|
Some Recent Research
Projects |
|
|
|
|
Post Installation Tools |
|
Embedded post foundations are largely responsibility for the cost
effectiveness of the post-frame building system. However, like other
foundation systems, installation of embedded post foundations has its
unique challenges. To help overcome some of these difficulties,
prototypes of three different tools: a posthole installation shield, a
posthole-bottom leveler, and a footing transport and placement cart were
designed by Bohnhoff and tested in 2003. Research in 2004
was concentrated on refinement of the posthole-bottom leveler.
Research in 2005 resulted in a new version of the footing transport and
placement cart and modifications to the posthole installation shield.
The posthole-bottom leveler is a
simple, inexpensive device used to level soil at the base of a hole
prior to tamping and placement of a precast concrete footing (a.k.a.
cookie). The use of such a device becomes increasingly important as
footing diameter increases. Without such a device it is difficult to
ensure that the base of a hole is not tilted or uneven. A tilted base
results in a tilted footing, and consequently, a significantly reduced
area of contact between the footing and post. Uneven terrain (i.e.,
high and low points) results in more variant footing stresses and
increases the likelihood of future foundation settlement. It is
recommended that such a tool be present on any jobsite where precast
concrete footings are being placed.
Sloughing of posthole sides is associated with drilling in noncohesive
soils (e.g., sands and gravels with low clay contents) that are of low
density, poorly compacted, very wet because of a recent rain or because
they are poorly drained, or saturated because they are near or below the
water table. Vibrations that occur when hitting rocks and/or tree roots
generally increase the likelihood of posthole collapse. When a posthole
side sloughs, the diameter at the top of the posthole becomes larger.
This makes in more difficult to throw material away from the posthole by
spinning the auger after it has been brought to the surface. It also
becomes more difficult for workers to prepare the base of the posthole
for a footing, to place the footing, and to properly position, brace and
backfill the post, even when planking is used to bridge the large
opening. The posthole installation shield is used to
prevent posthole sides from collapsing during hole drilling and anytime
prior to footing and post installation. It is recommended that all major post-frame companies
stock one or more post-hole installation shields for use on jobsites
where conditions make it difficult to maintain proper posthole geometry.
Round, precast footings (a. k. a. cookies), especially those with
diameters less than 17 inches, are frequently dropped into postholes.
Unfortunately, regardless of its size, the likelihood of a “dropped”
footing landing properly in a hole is extremely remote. When one edge of
a footing hits first, the result is a localized soil bearing failure – a
failure involving the movement and “loosening up” of a good portion of
the surrounding soil. To avoid damage to the footing base, some
contractors use special tongs to lower smaller footing. Others have
wrapped steel banding around the footing, and then removed it after the
footing was in place. Neither of these methods works very well with
larger/heavier footings. Footings that are too large for one person to
lift up are typically handled with a rough terrain forklift, skid steer
loader, front-end loader tractor or similar piece of equipment. This
equipment is not only used to move footings around on the jobsite, but
they are also frequently used to lower larger footing into postholes.
In addition to the equipment operator, another worker is typically
required to attach/detach footings to/from the equipment and to guide
the footings so they do not hit the posthole sidewalls when being
lowered. In other words, it requires two workers and a larger piece of
equipment to properly install large precast footings. The footing
transport and placement cart enables a single person to transport
and place precast concrete footings as large as 350 lbm and 34 inches in
diameter, without the use of self-propelled equipment. Any company
that stocks and/or routinely uses footings weighing in excess of 100 lbm
should not be without a footing transport and placement cart.
There are no patents protecting the three post installation tools
described above. They are
provided for public use and to stimulate development of similar tools.
In return, we simply ask that any individual or company that uses the
designs, or in anyway profits from the designs, help support through
donation, the post-frame building research effort at the University of
Wisconsin-Madison. University research is a non-profit venture that can
only be sustained via constant support from those who it benefits. |
|
|
|
Lateral Load Distribution in a
Metal-Clad Wood-Frame Building |
|
This project involved the construction and testing of a full-scale,
metal-clad, post-frame building with the goal of gaining a better
understanding of the complex distribution of load in this popular
agricultural building system. The building was erected, instrumentation
was installed, and initial tests conducted in 2001. Research in 2002
was dedicated entirely to testing and analysis of data. Research in
2003 and 2004consisted of data analysis and computer modeling.
The test building is 40- by 200-ft with trusses on 10 foot centers.
Trusses are pin-connected to posts, which in turn are pin-connected to
concrete piers. Centered under each interior truss is a hydraulic frame
loader (HFL) that is attached by rods to each end of the truss. An HFL
can be set to operate in one of four modes: (1) north load, (2) south
load, (3) lock, or (4) float. Although there are no HFLs under the
endwall trusses, the endwalls trusses can be either locked-in-place or
allowed to float during a test.
Using the versatility of the HFLs, 22 different loading were applied to
each of 10 different building configurations. Different building
configurations were obtained by adding and removing: the ridge, chord
reinforcing hardware, roof-to-sidewall fasteners, roof panel stitch
screws, sidewall steel, and eave trim. This experimental design was
replicated twice for a total of 440 building tests in 2002. During each
test signals from 225 different transducers were recorded every 4.7
seconds. With a test time of at least 3 minutes each loading usually
generated at least 10000 data points. This was obviously an unwieldy
amount of data to analyze without significant data reduction.
Throughout early 2003, research effort was primarily dedicated to data
reduction. This was accomplished by first calculating an average
horizontal frame force for each 4.7 second scan. The second step in
data reduction was to linearly regress the output from each transducer
on the average horizontal frame load values. After these regression
analyses, the data file for each load case was reduced to 204 values.
During the latter part 2003 and
throughout 2004, research effort was dedicated to the modeling of
full-scale building behavior. In the end, a model with three
displacement degrees of freedom (DOF) per building frame was selected.
These include a displacement parallel to the frame, and two
displacements perpendicular to the frame – one at each side wall. The
3-DOF/frame model contains four different simple spring elements (a.k.a.
truss elements): a frame element, roof cladding element, chord element
and wall cladding element.
The primary task during the
modeling phase of the study was to determine axial stiffness properties
for each of the four elements, or more specifically, to find element
stiffness values that were a function of building configuration, and
thus could be used to accurately predict full-scale building behavior
regardless of building configuration or distribution of applied loads.
This turned out to be a formidable task, requiring thousands of computer
simulations because of the interdependency of wall cladding, roof
cladding and chord force element properties. Nevertheless, a set of
element properties were selected that do a very good job of predicting
building displacements as well as the in-plane bending moment and shear
forces between building bays. The results of this modeling were
presented at the 2004 ASAE/CSAE International Meeting in Ottawa,
Ontario.
The 3-DOF/frame model is embodied
in computer program DAFI3 (Diaphragm And Frame Interaction 3 dof/frame).
Once a pre- and post-processor are added to the program, it will be made
available to the general public.
As part of this ongoing study, a closer assessment of chord forces will
be undertaken. This should ultimately lead to improvements
in current standards for diaphragm design. |
| |
|
Accuracy of Corrugated Metal Panel
and Trim Installation |
|
In January of 1999, the National Frame Builders Association (NFBA)
published Accepted Practices for Post-Frame Building Construction:
Framing Tolerances. In preparing this document, UW-Madison
researchers conducted an extensive field investigation to determine just
how accurately post-frame building frames are constructed.
In March of 1999, the NFBA Technical and Research (T&R) Committee
proposed that NFBA pursue the development of a second construction
tolerances document; one that covered metal trim and corrugated panel
installation. In October of 2002, the committee identified items for
inclusion in the document. At this same meeting, it was agreed that
University of Wisconsin-Madison researchers would conduct the field
research required for document development.
Actual data collection commenced during the summer of 2003 and was
completed in early June, 2004. A total of 52 buildings were surveyed.
Items investigated included: (1) panel plumbness; (2) roof-to-wall
panel rib alignment; (3) corner trim squareness; (4) corner trim
connection to wall panel; (5) wainscot panel alignment; (6) roof panel
offsets at eaves; (7) variations in roof panel overhang; (8)
misalignment of wall panel ends (e.g., saw-tooth effect); (9) fit at
openings; (10) dings; (11) scratches and scrapes; (12) crimps/kinks;
(13) horizontal fastener alignment; (14) fastener drive depth; (15)
fastener driving angle; (16) fasteners missing framing; and (17)
irregular fastener patterns.
Data from field investigations were tabulated and analyzed, and then
summarized in a technical paper presented at the 2004 ASAE/CSAE
International Meeting in Ottawa, Ontario. This information was
subsequently used by Bohnhoff to draft the first version of a document
entitled Accepted Practices for Post-Frame Building Construction:
Metal Panel and Trim Installation Tolerances. This document went
through five revisions based on feedback from the NFBA T&R Committee.
The final version was assembled by Bohnhoff in August of 2005, at which
time it became an official NFBA document. |
| |
|
Concrete Pier-to-Wood Post Connector
Design |
|
A greater number of post-frame buildings are being constructed using
precast or cast-in-place concrete piers. This increased interest in concrete piers can be attributed to following seven,
largely-interrelated reasons.
-
Durability.
End users have more confidence in the long-term durability of a
concrete foundation than they do in a preservative-treated wood
foundation. This is largely due to the poor performance of many
under-treated solid–sawn posts. It is important to
note that to date, they are no documented failures of
mechanically-laminated wood posts that have been properly treated
for ground contact with CCA (chromated copper arsenate)
-
Reduced availability and/or higher cost of CCA-treated
lumber. Effective December 31, 2003, no wood treater or manufacturer could treat
wood with CCA for most residential uses.
While posts for agricultural and commercial buildings can still be CCA-treated,
the partial ban on CCA significantly reduces the amount of wood that is
CCA-treated, making it more difficult and expensive to obtain.
-
Corrosiveness of CCA alternatives.
Alternative CCA treatments include ACQ (Alkaline Copper Quat) and ACC (Acid Copper
Chromate). Like CCA, these alternative treatments rely on copper
toxicity for effective protection from decay organisms. Unlike CCA,
they are not time-tested and tend to leach more copper into the
environment. To combat leaching, more copper is used in initial wood
treatment. This
higher copper concentration results in yet more loss of copper, and
increased galvanic corrosion when metals less noble than copper
(e.g., magnesium, zinc, iron, steel, aluminum) are driven into or
brought into direct surface contact with the treated wood. Excessive corrosion of metal fasteners is of primary
concern to engineers concerned about structural integrity and hence
safety of building occupants.
-
Reduced use of
preservative treated lumber. Where possible, engineers try to
eliminate preservative-treated lumber because (1) it costs more than
non-treated lumber, (2) it generally requires use of more expensive,
less-corrosive fasteners, and (3) preservative wood treatments are
pesticides which can make eventual disposal of preservative-treated
wood problematic. The cost of preservative
treatment alone will drive engineers to use posts featuring treated
wood spliced to untreated wood in an effort to save money for posts
not requiring above ground treatment. Use of concrete piers in this
situation eliminates the treated wood altogether, as well as the
additional assembly costs associated with joining treated to
untreated dimension lumber.
-
Lumber length. Lumber becomes increasingly expensive (on a
board foot basis) in longer lengths. Additionally, dimension lumber
is not readily available in lengths longer than 20 feet. When
concrete piers are used, the overall length of the wood post is
generally shortened by four to seven feet. This means engineers are
using shorter, less expensive lumber to obtain the same building
heights, and can also build structures with 20 foot eave heights
using unspliced sidewall posts.
-
Ease of building
disassembly. Agricultural and commercial buildings have a
relatively short functional design life. It is therefore beneficial
to be able to easily disassembly the building components for use in
a more functional structure. This is much easier to accomplish when
wood posts are attached to concrete piers.
-
Recycling. If history teaches us anything, it is that reuse
of lumber treated with a particular preservative is largely dictated
by restrictions placed on use of the preservative after it has been
in use for several years. For example, it is not possible to
reuse lumber treated with pentachlorophenol in buildings because
of restrictions placed on its use in 1984 (pentachlorophenol is no
longer available to the general public, although it is still used
industrially as a wood preservative for utility poles, railroad
ties, and wharf pilings). Some researchers have suggested that the development of good
organic-based preservative wood treatments may result in restricted
use of all heavy-metal based preservatives, thus making products
treated with CCA, ACQ and ACC of little value several years from
now. If this is the case, anything that can be done to replace
preservative-treated wood with untreated wood may increase future value of a
building.
Despite the increased use of concrete
piers in post-frame building construction, and the number of
post-frame buildings that have been erected on concrete frost walls
and grade beam foundations, very little attention has been focused
on concrete-to-wood post connections. Common steel brackets used by the post-frame
industry to attach wood posts to cast-in-place concrete
are treated as pin connections in design because of the lack of
bending strength and stiffness of (1) the steel bracket-to-concrete
connection, (2) the steel bracket-to-wood post connection, and/or
(3) the steel bracket itself . With concrete-to-wood post
connections that lack bending strength and stiffness, the building
designer must rely entirely upon diaphragm action and/or on
rigid column-to-truss connections to handle horizontal
forces applied to the structure.
Development of a concrete-to-wood post
connection with significant bending strength and stiffness will
help concrete piers with attached wood posts behave like unjointed
beams. This would enable design engineers to either reduce overall
post size, or rely less on diaphragm action or rigid frame design
for building stability. This, in turn, would make concrete piers
more attractive to builders, which would ultimately decrease
dependence on preservative-treated lumber. |
| |
| |
|